Category: Steel Detailing Blog

This page show cases some of the Steel Detailing projectgs completed in Melbourne, Sydney, WA, Brisbane Tek1 has completed

  • EMU IN THE SKY:Branches

    EMU IN THE SKY:Branches

    Continuing from our previous blog on the EMU IN THE SKY project, this post delves into the challenges and solutions for positioning the branches into the globe structure.

    Challenges with the Original Design

    The initial structural design, while visually impressive, posed significant challenges during the erection phase. The lack of tolerance in positioning the branches made the process more complicated, increasing the risk of errors and time-consuming adjustments.

    EMU team proposal

    To overcome this, the team introduced:

    Circular Plates with Holes: A circular plate with pre-drilled holes was introduced, allowing for precise alignment of the branches.

    Slotted Holes in the Outer Stub: Slotted holes were added to the outer stub welded to the globe. This innovation offers adjustable positioning, making the assembly process significantly easier and more efficient

    In this method we can place the branches plate in any rotation.

    Why This Design is Feasible

    The updated design not only simplifies the erection process but also reduces the likelihood of rework. The added tolerances ensure that branches can be positioned accurately with minimal effort, saving both time and resources.

    Stay tuned for more updates on the EMU IN THE SKY project as we continue to share insights and innovations from this iconic endeavor.

  • Maximum Cleat Heights for Purlins and Girts

    There are recommended maximum heights for purlins and Girts. If you want more heights the options are increase cleat thickness ore change cleat profile to may be equal angle profile.

    Expert steel detailers will know what to do and will use the appropriate thickness and profile

    If you are using 8 mm plate cleat, you can go upto 150 mm max

    Beyond that use an EA cleat

    75×6 EA is good.

    Increasing plate thickness may not be a good option because of PB30 bolt where the bolt length is only 30 mm.

  • Steel Fabrication Drawing

    Steel Fabrication Drawing

    Workshop drawings for balustrades of Bridge#84 Dynon Road Walking & Cycling bridge, West Melbourne.

    The fabrication drawings for the 230-meter-long balustrade panels, which feature vibrant, rainbow-colored finishes were delivered with NIL mistakes and on time.

    Challenges in the As-Built Stage

    One of the most intriguing aspects of this project was the challenge posed by the as-built ramp slope and its curve, which deviated significantly from the original design coordinates. These deviations added a layer of complexity to detailing the balustrades, as each panel had to align perfectly with the precast kerbs.

    To address this, we worked closely with the builder and requested precise site measurements. These measurements were essential for us to adjust our detailing to account for the as-built ramp’s unique coordinates, ensuring every panel fit perfectly into place.

    Tailored Solutions for On-Site Realities

    The balustrade panels were fixed to the precast kerbs using as-built ferrules, demonstrating the adaptability required in projects where site conditions differ from the initial design. By leveraging the site measurements provided, we completed the detailing of all balustrades with precision, overcoming the complexities introduced by the ramp’s deviations.

    Conclusion:

    The Dynon Road Walking & Cycling Bridge is not just a pathway; it’s a vivid example of how meticulous detailing and innovative problem-solving can overcome challenges to deliver exceptional results. Its rainbow-colored balustrades are now a standout feature in West Melbourne, adding vibrancy and charm to the community.

  • Adding details without approval which affects other trades

    This memo clarifies the process for handling drawing approvals and issuance to ensure project coordination and minimize potential errors.

    Drawing Approval Reviews:

    When receiving approved drawings, carefully review them for any markups that may significantly impact other trades or existing structural elements (e.g., slabs, foundations, anchor bolts).

    Example: If an approved drawing introduces a slab pocket where none existed in the original design, ensure the following steps are taken:

    • Verify Slab Status: Issue an RFI (Request for Information) to determine the current status of the slab construction.
    • Coordinate with Relevant Parties: Communicate the design change to the construction crew responsible for pouring the slab.
    • Provide Updated Drawings: Issue revised slab drawings reflecting the pocket addition.

    Failure to take these steps can lead to costly rework and project delays.

    Issuing Drawings Before Approval:

    Construction drawings should only be issued prior to approval if specifically requested by the client. In such cases, the drawings must be clearly marked and include a disclaimer.

    Scenario 1: Client Does Not Require “For Construction” Marking

    • Issue a full set of drawings marked “Issued for Approval” (IFA).
    • Include a disclaimer stating that the drawings are not yet approved and their use is at the client’s own risk.

    Scenario 2: Client Requires “For Construction” Marking

    • Issue the drawings marked “For Construction.”
    • Include a disclaimer stating that the client was informed of the drawings’ unapproved status but requested them for construction at their own risk.
    • Obtain a written statement from the client acknowledging their request and acceptance of responsibility.

    This process ensures clear communication and accountability in the drawing issuance process, mitigating potential risks associated with using unapproved drawings.

  • Compliance with AS 1428.1 and BCA: Limiting Riser Openings to 125 mm in Commercial Staircases

    Compliance with AS 1428.1 and BCA: Limiting Riser Openings to 125 mm in Commercial Staircases

    If you would like me to assist with your project, please send an email to koshy@tek1.com.au with your project specifications. Kindly use ‘Raj’ as the subject header.

    When performing detailed engineering for commercial staircases and balustrades, it’s essential to ensure that all aspects comply with AS 1428.1 and the relevant provisions from the Building Code of Australia (BCA), particularly those regarding accessibility and safety. Here’s a breakdown of the critical points you must address:

    Compliance with AS 1428.1:
    1. This standard outlines the minimum technical requirements for accessible buildings. Engineers must reference the BCA to align with safety and access provisions. AS 1428.1 directs engineers to follow BCA for detailed requirements related to stair and balustrade design, ensuring all safety standards are met, particularly for disabled access.

    2. BCA 3.9.1.3 – Riser Opening Requirement:
    One of the key safety provisions under BCA 3.9.1.3 is ensuring that the riser openings on stairways are restricted. Specifically, the gap between treads must not allow a 125 mm sphere to pass through. This rule is vital for preventing accidents, such as children slipping through open risers. As a detailed engineer, you must ensure that this riser opening specification is incorporated into the technical drawings and calculations to meet safety compliance.

    3. BCA 3.9.1.4 – Riser and Going Dimensions:
    Further, BCA 3.9.1.4 provides specific dimensional requirements for stair risers and goings, as illustrated in Figure 3.9.1.2. This figure shows the maximum and minimum values for risers (R) and goings (G), as well as the slope relationship (2R + G). Engineers must adhere to these dimensions for both spiral and non-spiral staircases to ensure that the stairs are not only safe but also ergonomically comfortable for users.

    4. Critical Figures:

    Riser (R): Must be within the maximum and minimum values—115 mm to 190 mm for standard stairs and 140 mm to 220 mm for spiral stairs.

    Going (G): Must be within the maximum and minimum values—240 mm to 355 mm for standard stairs and 210 mm to 370 mm for spiral stairs.

    Slope Relationship (2R + G): Must fall between 550 mm and 700 mm for standard stairs and 590 mm to 680 mm for spiral stairs. These values ensure that stairs provide both safety and comfort.

    5. Ensuring Compliance:
    As part of the detailed engineering process, it’s your responsibility to ensure that all specifications, such as the 125 mm riser opening limit and the exact riser and going dimensions, are strictly followed in the drawings, materials, and construction processes. This involves validating these measurements on-site and ensuring they are reflected accurately in both the design and construction stages.

    In conclusion, the detailed engineering process must ensure compliance with AS 1428.1 and the BCA, particularly regarding the requirement that the riser opening must not exceed 125 mm, as outlined in BCA 3.9.1.3. Additionally, the riser and going dimensions must conform to the standards specified in BCA 3.9.1.4. By adhering to these standards, you will ensure that commercial stairs and balustrades are safe, accessible, and compliant with Australian building regulations.

  • Address Erection Feasibility While Detailing Structural Steel

    Address Erection Feasibility While Detailing Structural Steel

    The Issue:

    • According to the design, the bottom angle (as shown in the below design) is welded to the truss chord and top angle is welded to another frame.
    • However, this creates a challenge when it comes to erecting the top angle, since both top and bottom angles need to be bolted together.
    • The all-around weld on the bottom angle complicates the positioning of the top angle, as the weld at the top obstructs proper placement.

    How did we resolve the issue?

    Ensure that no weld is applied at the top of the bottom angle. This makes it easier to  position the top angle during erection.If the welding had already been completed, you could grind the weld at the top of the bottom angle. This would afford enough clearance for the top angle to be fitted.

  • Safety Standards in Building Design – Key Requirements for Barriers, Handrails, and Fall Prevention

    Safety Standards in Building Design – Key Requirements for Barriers, Handrails, and Fall Prevention

    If you would like me to assist with your project, please send an email to koshy@tek1.com.au with your project specifications. Kindly use ‘Raj’ as the subject header.

    1. Barriers to Prevent Falls (Section 11.3.3)

    • Purpose: Barriers are required on various elevated surfaces to prevent falls.
    • Where Required: Install barriers along stairways, ramps, balconies, and any surface where a fall of 1 meter or more is possible. (see Figure 11.3.3a).
    • Exceptions:
      • Retaining walls (unless they are part of an access path). (see Figure 11.3.3b).
      • Certain window openings covered by specific provisions. (see Figure 11.3.7 and 11.3.8).

    2. Barrier Construction Standards (Section 11.3.4)

    • Height Requirements:
      • Stairs/Ramps: Minimum 865 mm above the stair treads or ramp floor. (see Figure 11.3.4a).
      • Other Elevated Surfaces: Minimum 1 meter for landings, balconies, and similar elevated areas. (see Figure 11.3.4a).
    • Design for Child Safety:
      • Openings in barriers should not allow the passage of a 125 mm sphere, the opening is measured above the nosing line of the stair treads, minimizing the risk of children slipping through. (the opening is measured above the nosing line of the stair treads)
      • Avoid horizontal elements between 150 mm and 760 mm above the floor, as they can facilitate climbing​. (see Figure 11.3.4b).

    3. Handrail Requirements (Section 11.3.5)

    • Placement: Handrails should be installed on at least one side of stairways or ramps, providing continuous support along their full length.
    • Height: The top of the handrail must be at least 865 mm above the stair treads or ramp surface. (see Figure 11.3.4b).
    • Continuity: Handrails should be continuous without interruptions, with exceptions for elements like newel posts.
    • Exceptions to Handrail Requirements:
      • Handrails are not necessary for stairways or ramps with elevation changes of less than 1 meter, on landings, or for winders with a newel post for support​

    This guide emphasizes key elements in designing safe, compliant buildings that align with the Australian Building Codes Board (ABCB) standards for fall prevention, especially around barriers and handrails. These regulations aim to protect all building users, especially vulnerable groups such as children, from potential fall hazards.

  • Concrete and Steel – Hidden Snags to Watch out For –A Case Study in Duffy’s Forrest – An Example of Something that can Kill your client

    Concrete and Steel – Hidden Snags to Watch out For –A Case Study in Duffy’s Forrest – An Example of Something that can Kill your client

    “In the world of steel detailing, failing to account for concrete variances can cost your client dearly. This case study from Duffy’s Forest serves as a vital reminder of why site surveys in steel detailing are non-negotiable. Without accurate site measurements, you risk massive on-site rectification costs—including crane hire and specialized labor crews—that can easily exceed thousands of dollars.”

    Anyone who’s a detailer should be aware of this issue.

    If you’re not aware: you can cost your client dearly. How?

    • On site rectification costs:
    • crane, ($500 / hour for example)
    • crew: supervisor, boiler makers, riggers (x2) – it become expensive.

    You need operations to occur as fast as possible. This means you have to advise your client about potential issues.

    Consider the following:

    What is an issue that can kill your client regarding the below:

    Lessons Learned:

    • The concrete has already been poured.
    • But the steel has not yet been cut and fabricated.
    Concrete in Steel Detailing

    Check out the live model link here to Duffy’s Forrest.

    Be warned:

    • We keep repeating this again and again: very rarely is the concrete where it should be!
    • The pockets may not be properly aligned.
    • The pockets may be too deep – as it was in this case.
    site-survey-steel-detailing-case-study

    How Steel Detailers Can Prevent Costly On-Site Errors.

    • Detailers should ensure that their clients conduct site surveys to ensure everything is ok.
    • Detailers should make sure that the pockets are the correct depth.

    In this case the pockets were too deep – this means that the columns need to be lengthened.

    If the columns were not lengthened, then once it is taken to site – nothing would fit. And now site rectification costs would be immense.

    Expert Steel Detailer | Melbourne | Sydeny

  • Memo 41: Be aware of Risks, Transportation and Site Costs when making changes

    Engineer says, make the change to a little cleat.

    And then fabricate. No need to re-submit for stamping.

    But should you?

    Just a little cleat?

    Except it’s on the end of a 15m beam.

    What’s the problem with that?

    • 15m beams are not standard size.
    • They need to be placed on oversized trucks. Trucks ain’t cheap.
    • This means that they they can only be transported outside business hours – big trucks will slow down traffic.
    • Also you need a special crane to lift such large beams into place. They ain’t cheap: $600 per hour. And remember, you cannot just hire it for one hour, you have to hire it for an entire day / week.
    • If there’s a problem with the cleat, then you might find it difficult to fix on site. This means you have to bring the beam back down to the ground. Where are you gonna keep it?
    • Are you going to send the truck away? Of course not – you’ll need the truck.
    • And you’ll need the crane for an extra day.
    • And you’ll need to pay overtime rates.

    ……..so the question is, if something goes wrong, who’s carrying the can?

    What should you do?

    Make sure everyone’s on the same page. Seek an approval from the engineer. When everything’s fine, then party keeps going. But when there’s a mistake, and huge costs, and liquidated damanges, fingers will be pointed.

    Make no mistake, they want you to carry the can.