Category: Steel Detailing Blog

This page show cases some of the Steel Detailing projectgs completed in Melbourne, Sydney, WA, Brisbane Tek1 has completed

  • Millar Warehouse

    Millar Warehouse

    Detailed by Ganesh & team

    Tek1 has successfully completed the industrial project for the reputed organisation in Australia.

    This project does not have any structural design drawings. Instead, the client has provided sample design drawings. Therefore, we need to coordinate our structural design with the architect’s drawings.

    Detailed by Ganesh & team

    We need to provide structural support for an overhead crane. TEK1 has provided the correct beam profiles for the structural support, and the client is satisfied with our design and shop drawings.

    Detailed by Ganesh & team

    Our main objective is to deliver high-quality drawings without any errors. TEK1 has successfully achieved this goal.

  • Glenfern Lifestyle park

    Glenfern Lifestyle park

    Detailed by Ganesh & team

    Tek1 has successfully completed the project for the reputed organisation in Australia .

    Lots of timber connections involved with steel in this project. TEK1 provided all the supporting members for timber.Client is happy with the connections that we have provided which is not in their design.

    Gym area
    Sports bar

     

     

  • M4 Cut & Cover – Tunnel road ceiling support

    M4 Cut & Cover – Tunnel road ceiling support

    Detailed by Ganesh & team

    Tek1 has successfully completed the industrial project for the reputed organisation in Australia .

    We have provided a ceiling support steel for the tunnel road. One of the main challenges we faced in this project was site measurement. We had to provide frames between two walls, and modeling using design dimensions was not feasible.

    Detailed by Ganesh & team

    As a result, we decided to model all of the frames using the site measurements. We received measurements of the rock surface which was uneven, so we had to calculate the face-to-face dimensions for each frame and then proceed with the modeling process.

     

    We are thrilled to announce that this project has been successfully completed without any errors!

  • Preston tram shed

    Preston tram shed

    Tek1 has successfully completed the industrial project for the reputed organisation in Australia .

    Lots of site measure involved in this project. TEK1 coordinated with builder & surveyor to finish the project without any error. Client is happy with our work.We are always focus on the client requirements.

  • Add Bent Plate or Welded Plates

    For the fabricator, bent plates are more expensive to produce in low volume. So when you want a bent plate, in low volume ( less than 50 pieces, go for welded plates). More than that please raise an RFI. When you are detailing please note this one.

  • St. Benedict’s Stage 7 Hall, Oran Park

    St. Benedict’s Stage 7 Hall, Oran Park

    Raj (Arokiaraj Arputharaj)

    St. Benedict’s Stage 7 Hall, Oran Park, is a multipurpose hall structure.

    St. Benedict’s Catholic College was opened in 2011 on a greenfield site in Sydney’s south west suburb of Oran Park. 
    There are seven stages of construction work listed below.

    • Technology and Applied Studies (TAS)
    • food technology
    • covered outdoor learning
    • science
    • staff administration
    • library
    • creative and performing arts
    • general learning areas
    • multi-purpose hall 

    TEK1’s scope was Muti-Porspose Hall, and works included anchorbolt steel columns, beams, braces, and purlins.

    TEK1 raised multiple RFIs with a proposal. So the design got revised according to the RFIs.

    The client responded to TEK1 RFIs quickly.

    The project was completed  quickly by our team.

  • Bega Tafe – Stage 2

    Bega Tafe – Stage 2

    Raj (Arokiaraj Arputharaj)

    Bega Tafe-Stage 2 structure is Multi Trades Hub.

    The new 2-level Multi Trades Hub adjoins the existing TAFE NSW Connected Learning Centre and incorporates workshops for automotive, engineering, carpentry, and bricklaying disciplines. Also included are general learning spaces, specialist facilities that support the delivery of aged care, disability courses, and early childcare, as well as a specialised outdoor area for horticulture.

    TEK1 works included anchorbolt steel columns, beams, braces, and purlins.

    TEK1 raised multiple RFIs with a proposal. So the design got revised according to the RFIs. The client responded to TEK1 RFIs quickly. The project was completed quickly by our team.

  • 4 Schofield St, Essendon

    4 Schofield St, Essendon

    Raj (Arokiaraj Arputharaj)

    4 Schofield Street is a multi-residential development structure.

    The structure contained five dwellings. TEK1 raised multiple RFIs with a proposal. So the design got revised according to the RFIs.

    The client responded to TEK1 RFIs quickly.

    The project was completed quickly by our team.

  • Getting the Drawings Reviewed

    Getting the Drawings Reviewed

    Drawings are always submitted for approval before fabrication. When any changes are given by the structural engineer or the architect, after implementing the changes, the drawings must be submitted again for 2nd approval so that the structural engineer & the architect will review & approve the drawings.


    In some cases, the architect & the structural engineer skip their duty of reviewing & question the detailer whether the detailer has implemented all the changes. Refer below image for an example.


    In such cases answering with a “yes” might cause trouble to the detailer & the corresponding concern in he future.


    Rather than answering the question, the detailer can pose a question to the question asked like “Have the Structural Engineer and Architect approved?”.
    By such way, the detailer has attended to the structural engineer or the architect and also the duty to review the drawings has also been assigned once again to him.